CPM Scheduling
As a civil engineer, CPM scheduling is how you plan and track construction projects. You identify activities, durations, and dependencies, then compute early/late start and finish times. The forward pass finds the earliest each activity can start; the backward pass finds the latest without delaying the project. Activities with zero total float form the critical path — any delay on the critical path delays the entire project.
Earned Value Management
As a civil engineer managing a project, earned value analysis lets you track cost and schedule performance simultaneously. BCWS is what you planned to spend, BCWP is the budgeted value of work completed, and ACWP is what you actually spent. Cost and schedule variances tell you if you are over/under budget and ahead/behind schedule. Performance indices (CPI, SPI) and forecasting formulas (ETC, EAC) predict total cost at completion.
Project Delivery & Safety
As a civil engineer, you work within different project delivery systems — design-bid-build, design-build, and CM-at-risk — each allocating risk and responsibility differently. You also must understand OSHA construction safety requirements: excavation protection at 5 ft, fall protection at 6 ft, and PE-designed systems for excavations deeper than 20 ft. These topics appear as scenario-based questions on the FE.