FE Civil Engineering Economics practice problems

11 exam-style problems with worked solutions and the FE Reference Handbook page for each. Pick an answer to check it. No account needed.

Q1A municipality signs a 6-year equipment lease that requires a payment of 18,000 dollars at the end of each year. At an interest rate of 8%, what is the present worth of all the lease payments?

Worked solution

You have a series of equal annual payments (AA) and you want their value today (PP), so the factor is the uniform series present worth (P/A)(P/A). Look up (P/A, 8%, 6)=4.6229(P/A,\, 8\%,\, 6) = 4.6229 and multiply by 18,000 to get about 83,200. The 108,000 option just adds up the six payments (18,000×618{,}000 \times 6) with no discounting, ignoring the time value of money. The 88,500 option uses the wrong interest rate, applying (P/A, 6%, 6)=4.9173(P/A,\, 6\%,\, 6) = 4.9173 instead of the 8% factor. The 11,300 option treats the whole stream as a single future lump sum and discounts it with (P/F)(P/F) instead of (P/A)(P/A).

  1. Identify: A=18,000A = 18{,}000, i=8%i = 8\%, n=6n = 6 years. Find PP.
  2. Use the uniform series present worth factor:
    (P/A, 8%, 6)=(1.08)6−10.08(1.08)6(P/A,\, 8\%,\, 6) = \frac{(1.08)^6 - 1}{0.08(1.08)^6}
  3. Compute the factor:
    (1.08)6=1.58687  ⇒  (P/A)=0.586870.12695=4.6229(1.08)^6 = 1.58687 \;\Rightarrow\; (P/A) = \frac{0.58687}{0.12695} = 4.6229
  4. Calculate the present worth:
    P=18,000×4.6229=83,212≈83,200P = 18{,}000 \times 4.6229 = 83{,}212 \approx 83{,}200

FE Reference Handbook 10.6, p. 235, Uniform Series Present Worth; p. 241, Factor Table i = 8%

Q2Maintenance on a pump station is 5,000 dollars in year 1 and increases by 1,000 dollars each year thereafter (6,000 in year 2, 7,000 in year 3, and so on) for a total of 8 years. At an interest rate of 10%, what equivalent uniform annual cost represents this rising expense?

012345678A = 5,000G = 1,0005,00012,000i = 10%
Worked solution

The cash flow is a flat base of 5,000 dollars per year plus a uniform gradient G=1,000G = 1{,}000 that starts in year 2. Convert the gradient to an equivalent annual amount with the gradient-to-uniform factor (A/G, 10%, 8)=3.0045(A/G,\, 10\%,\, 8) = 3.0045, then add it to the base: A=5,000+1,000×3.0045=8,004≈8,000A = 5{,}000 + 1{,}000 \times 3.0045 = 8{,}004 \approx 8{,}000. The 8,500 option uses the simple arithmetic average of the gradient (1,000×7/2=3,5001{,}000 \times 7/2 = 3{,}500 added to 5,000), which ignores the time value of money. The 3,000 option reports only the gradient component and forgets to add the 5,000 base. The 12,000 option is the final-year cost (5,000+1,000×75{,}000 + 1{,}000 \times 7), not the annual equivalent.

  1. Identify the structure: base annuity Abase=5,000A_{\text{base}} = 5{,}000 plus uniform gradient G=1,000G = 1{,}000, with i=10%i = 10\% and n=8n = 8.
  2. Gradient-to-uniform factor:
    (A/G, 10%, 8)=1i−n(1+i)n−1=10.10−8(1.10)8−1(A/G,\, 10\%,\, 8) = \frac{1}{i} - \frac{n}{(1+i)^n - 1} = \frac{1}{0.10} - \frac{8}{(1.10)^8 - 1}
  3. Compute:
    (1.10)8=2.14359  ⇒  (A/G)=10−81.14359=10−6.9955=3.0045(1.10)^8 = 2.14359 \;\Rightarrow\; (A/G) = 10 - \frac{8}{1.14359} = 10 - 6.9955 = 3.0045
  4. Equivalent uniform annual cost:
    A=5,000+1,000×3.0045=8,004≈8,000A = 5{,}000 + 1{,}000 \times 3.0045 = 8{,}004 \approx 8{,}000

FE Reference Handbook 10.6, p. 235, Uniform Gradient (A/G); p. 241, Factor Table i = 10%

Q3A city plans to build a pedestrian bridge for 2,000,000 dollars that will require perpetual maintenance of 40,000 dollars per year forever. At an interest rate of 5%, what is the capitalized cost of the bridge?

Worked solution

Capitalized cost is the present worth of a project that lasts forever. For a perpetual uniform cost, the present worth of the annual maintenance is simply A/iA/i, so 40,000/0.05=800,00040{,}000 / 0.05 = 800{,}000. Add the one-time construction cost: 2,000,000+800,000=2,800,0002{,}000{,}000 + 800{,}000 = 2{,}800{,}000. The 2,040,000 option adds only one year of maintenance instead of capitalizing it over an infinite horizon. The 2,002,000 option multiplies the maintenance by the rate (40,000×0.0540{,}000 \times 0.05) instead of dividing. The 800,000 option gives only the capitalized maintenance and forgets the initial construction cost.

  1. Capitalized cost = initial cost + present worth of perpetual annual cost.
  2. Present worth of a perpetual uniform series:
    Pperp=Ai=40,0000.05=800,000P_{\text{perp}} = \frac{A}{i} = \frac{40{,}000}{0.05} = 800{,}000
  3. Add the initial construction cost:
    CC=2,000,000+800,000=2,800,000CC = 2{,}000{,}000 + 800{,}000 = 2{,}800{,}000

FE Reference Handbook 10.6, p. 236, Capitalized Cost

Q4A contractor compares two compactors. Compactor M costs 40,000 dollars, has annual operating costs of 10,000 dollars, no salvage value, and a 3-year life. Compactor N costs 60,000 dollars, has annual operating costs of 7,000 dollars, no salvage value, and a 6-year life. Using present worth analysis over the least common multiple of lives at MARR = 10%, which compactor is cheaper and what is its present worth of costs?

MARR = 10%Compactor M0340,00010,000/yrCompactor N0660,0007,000/yr
Worked solution

The lives are 3 and 6 years, so present worth must be compared over the least common multiple, 6 years. Compactor M must be purchased again at the start of year 4 (end of year 3). Its PW is 40,000+40,000(P/F, 10%, 3)+10,000(P/A, 10%, 6)=40,000+30,053+43,553=113,60640{,}000 + 40{,}000(P/F,\, 10\%,\, 3) + 10{,}000(P/A,\, 10\%,\, 6) = 40{,}000 + 30{,}053 + 43{,}553 = 113{,}606. Compactor N runs the full 6 years with no repeat: 60,000+7,000(P/A, 10%, 6)=60,000+30,487=90,487≈90,50060{,}000 + 7{,}000(P/A,\, 10\%,\, 6) = 60{,}000 + 30{,}487 = 90{,}487 \approx 90{,}500. N is cheaper. The "Compactor M, PW = 64,900" option compares only one 3-year cycle of M against nothing, an invalid unequal-life comparison. The "Compactor M, PW = 113,600" option is M's correct PW but M is the more expensive option. The "Compactor N, PW = 102,000" option forgets to discount M's replacement or mis-adds N.

  1. LCM of 3 and 6 is 6 years. Compactor M repeats once (replaced at end of year 3); Compactor N runs the full 6 years.
  2. Factors at 10%:
    (P/F, 10%, 3)=0.7513(P/A, 10%, 6)=4.3553(P/F,\, 10\%,\, 3) = 0.7513 \quad (P/A,\, 10\%,\, 6) = 4.3553
  3. Compactor M present worth of costs:
    PWM=40,000+40,000(0.7513)+10,000(4.3553)=40,000+30,053+43,553=113,606PW_M = 40{,}000 + 40{,}000(0.7513) + 10{,}000(4.3553) = 40{,}000 + 30{,}053 + 43{,}553 = 113{,}606
  4. Compactor N present worth of costs:
    PWN=60,000+7,000(4.3553)=60,000+30,487=90,487≈90,500PW_N = 60{,}000 + 7{,}000(4.3553) = 60{,}000 + 30{,}487 = 90{,}487 \approx 90{,}500
  5. Compactor N has the lower present worth of costs. Select Compactor N.

FE Reference Handbook 10.6, p. 235, Single Payment Present Worth + Uniform Series Present Worth; p. 241, Factor Table i = 10%

Q5A precast concrete plant sells wall panels for 450 dollars each. Its fixed costs are 90,000 dollars per month, and the variable cost to produce each panel is 270 dollars. How many panels must the plant sell per month to break even?

Worked solution

At break-even, total revenue equals total cost, so the contribution margin per panel (selling price minus variable cost) must cover the fixed cost. The margin is 450−270=180450 - 270 = 180 dollars per panel, and 90,000/180=50090{,}000 / 180 = 500 panels. The 200-panel option divides the fixed cost by the selling price alone and ignores the variable cost. The 333-panel option divides by the variable cost instead of the contribution margin. The 125-panel option divides by the sum of price and variable cost (450+270=720450 + 270 = 720) instead of their difference.

  1. Contribution margin per panel:
    p−v=450−270=180p - v = 450 - 270 = 180
  2. Set revenue equal to total cost: 450Q=90,000+270Q450Q = 90{,}000 + 270Q, which gives 180Q=90,000180Q = 90{,}000.
  3. Solve for the break-even quantity:
    Q∗=90,000180=500 panelsQ^* = \frac{90{,}000}{180} = 500 \text{ panels}

FE Reference Handbook 10.6, p. 236, Cost Estimation and Break-Even Analysis

Q6A construction firm owns a vacant lot it could lease to a neighboring business for 30,000 dollars per year. Instead, the firm decides to use the lot as an equipment staging yard for its own projects. In an economic analysis of using the lot for staging, how should the 30,000 dollars per year of forgone lease income be classified?

Worked solution

By choosing to stage equipment on the lot, the firm gives up the 30,000 dollars per year it could have earned by leasing it out. The value of the best forgone alternative is the definition of an opportunity cost, and it must be counted as a cost of the staging decision even though no cash actually changes hands. The sunk-cost choice confuses ownership with sunk cost: the lease income is a future, recoverable alternative, not money already spent and lost. The fixed-cost choice is wrong because the forgone income does not arise from operating the yard; it exists regardless of activity level. The marginal-cost choice misapplies marginal cost, which is the cost of one more unit of output, not a forgone alternative use of an asset.

  1. Using the lot for staging means the firm cannot lease it out, so it forgoes 30,000 dollars per year of income.
  2. Opportunity cost is the value of the best alternative given up when a choice is made.
  3. The forgone lease income is therefore an opportunity cost and should be charged against the staging-yard option.
  4. It is not a sunk cost (the income is a future alternative, not a past irrecoverable expense) and not a fixed or marginal cost of operating the yard.

FE Reference Handbook 10.6, p. 236, Cost Estimation; p. 235, Engineering Economics concepts

Q7A proposed highway widening has a present worth of user benefits of 8,000,000 dollars, a present worth of disbenefits (added noise and property impacts on adjacent residents) of 1,200,000 dollars, and a present worth of agency costs of 5,500,000 dollars. Using the conventional benefit-cost ratio with disbenefits subtracted from benefits, what is the B/C ratio?

Worked solution

Disbenefits are negative effects on the public, so they are subtracted from the benefits in the numerator: B/C=(B−D)/C=(8,000,000−1,200,000)/5,500,000=6,800,000/5,500,000=1.24B/C = (B - D)/C = (8{,}000{,}000 - 1{,}200{,}000)/5{,}500{,}000 = 6{,}800{,}000/5{,}500{,}000 = 1.24. The 1.45 option ignores the disbenefits entirely (8,000,000/5,500,0008{,}000{,}000/5{,}500{,}000). The 1.19 option incorrectly adds the disbenefits to the cost denominator (8,000,000/6,700,0008{,}000{,}000/6{,}700{,}000). The 1.86 option incorrectly subtracts the disbenefits from the cost denominator (8,000,000/4,300,0008{,}000{,}000/4{,}300{,}000) instead of from the benefits.

  1. Subtract disbenefits from benefits in the numerator:
    B−D=8,000,000−1,200,000=6,800,000B - D = 8{,}000{,}000 - 1{,}200{,}000 = 6{,}800{,}000
  2. Divide by the present worth of agency costs:
    B/C=6,800,0005,500,000=1.24B/C = \frac{6{,}800{,}000}{5{,}500{,}000} = 1.24
  3. Since B/C = 1.24 > 1, the project is economically justified.

FE Reference Handbook 10.6, p. 237, Benefit-Cost Analysis

Q8A developer must decide whether to build a mixed-use project now. Demand is uncertain: there is a 50% chance of high demand giving a net present value of +500,000 dollars, a 30% chance of medium demand giving +200,000 dollars, and a 20% chance of low demand giving -100,000 dollars. What is the expected net present value of building now?

Worked solution

At a chance node you weight each outcome by its probability and sum: EV=0.50(500,000)+0.30(200,000)+0.20(−100,000)=250,000+60,000−20,000=290,000EV = 0.50(500{,}000) + 0.30(200{,}000) + 0.20(-100{,}000) = 250{,}000 + 60{,}000 - 20{,}000 = 290{,}000. The 200,000 dollars choice takes the plain arithmetic average of the three outcomes ((500,000+200,000−100,000)/3(500{,}000 + 200{,}000 - 100{,}000)/3) and ignores the probabilities. The 330,000 dollars choice treats the low-demand outcome as a gain instead of a loss (adds 20,000 instead of subtracting). The 310,000 dollars choice drops the unprofitable low-demand branch entirely and sums only the first two terms.

  1. Confirm probabilities sum to 1.0: 0.50+0.30+0.20=1.000.50 + 0.30 + 0.20 = 1.00.
  2. Apply the expected value formula at the chance node:
    EV=0.50(500,000)+0.30(200,000)+0.20(−100,000)EV = 0.50(500{,}000) + 0.30(200{,}000) + 0.20(-100{,}000)
  3. Compute each term:
    EV=250,000+60,000−20,000EV = 250{,}000 + 60{,}000 - 20{,}000
  4. Sum:
    EV=290,000EV = 290{,}000

FE Reference Handbook 10.6, p. 237, Economic Decision Trees; Expected Value

Q9A contractor buys a backhoe for 150,000 dollars with an estimated salvage value of 30,000 dollars after an 8-year life. Using straight-line depreciation, what is the book value of the backhoe at the end of year 5?

Worked solution

Straight-line depreciation is constant each year: D=(C−Sn)/n=(150,000−30,000)/8=15,000D = (C - S_n)/n = (150{,}000 - 30{,}000)/8 = 15{,}000 per year. After 5 years the accumulated depreciation is 5×15,000=75,0005 \times 15{,}000 = 75{,}000, so the book value is 150,000−75,000=75,000150{,}000 - 75{,}000 = 75{,}000. The 56,250 option forgets to subtract salvage when computing the annual depreciation (150,000/8=18,750150{,}000/8 = 18{,}750 per year, then 150,000−93,750150{,}000 - 93{,}750). The 45,000 option wrongly subtracts the accumulated depreciation from the depreciable base (120,000−75,000120{,}000 - 75{,}000) instead of from the full cost. The 30,000 option assumes the asset is already at salvage value, which only happens at the end of its full 8-year life.

  1. Annual straight-line depreciation:
    D=C−Snn=150,000−30,0008=15,000D = \frac{C - S_n}{n} = \frac{150{,}000 - 30{,}000}{8} = 15{,}000
  2. Accumulated depreciation through year 5:
    ∑k=15Dk=5×15,000=75,000\sum_{k=1}^{5} D_k = 5 \times 15{,}000 = 75{,}000
  3. Book value at end of year 5:
    BV5=150,000−75,000=75,000BV_5 = 150{,}000 - 75{,}000 = 75{,}000

FE Reference Handbook 10.6, p. 236, Depreciation; Book Value

Q10A culvert replacement is estimated to cost 50,000 dollars in actual (then-current) dollars 10 years from now. The general inflation rate is 3% per year. Expressed in today's constant (real) purchasing-power dollars, what is the equivalent cost?

Worked solution

Converting an actual (inflated) future amount into today's purchasing power means dividing by the inflation index (1+f)n(1 + f)^n, not discounting at any interest rate: 50,000/(1.03)10=50,000/1.3439=37,205≈37,20050{,}000 / (1.03)^{10} = 50{,}000 / 1.3439 = 37{,}205 \approx 37{,}200. The 67,200 distractor multiplies by the inflation factor (50,000×1.343950{,}000 \times 1.3439), moving in the wrong direction. The 35,000 distractor applies a simple, non-compounded 30% reduction (50,000×(1−0.30)50{,}000 \times (1 - 0.30)). The 38,500 distractor divides by a simple factor of 1.30 instead of the compounded (1.03)10(1.03)^{10}.

  1. Identify: actual-dollar future cost =50,000= 50{,}000, inflation f=3%f = 3\%, n=10n = 10 years.
  2. Deflate by the inflation index to reach constant (real) dollars:
    Real=50,000(1+f)n=50,000(1.03)10\text{Real} = \frac{50{,}000}{(1 + f)^n} = \frac{50{,}000}{(1.03)^{10}}
  3. Compute the index:
    (1.03)10=1.34392(1.03)^{10} = 1.34392
  4. Result:
    Real=50,0001.34392=37,205≈37,200\text{Real} = \frac{50{,}000}{1.34392} = 37{,}205 \approx 37{,}200

FE Reference Handbook 10.6, p. 236, Inflation

Q11A project has an internal rate of return of 18%18\% and the firm's MARR is 12%12\%. According to rate-of-return analysis, the project should be:

Worked solution

Accept if IRR ≥ MARR. Here 18% ≥ 12%, so the project clears the hurdle and should be accepted. The "Rejected, because IRR exceeds MARR" choice reverses the rule. The "too high to be realistic" and "deferred until MARR rises above 18%" choices invent reasoning not part of the criterion.

  1. Rule: accept if IRR ≥ MARR.
  2. 18% ≥ 12%.
  3. So the project is accepted.

FE Reference Handbook 10.6, p. 236

11 problems. Your score shows here as you go.

New to Engineering Economics? Start with the FE Civil Engineering Economics study guide: what NCEES tests, the key formulas, and the mistakes that cost points.