20 exam-style questions that cover every topic on the FE Civil exam, weighted the way NCEES weights the real test. Pick an answer to check it, and the worked solution opens with the FE Reference Handbook page you would use on exam day. No account needed.
How this practice exam is built
The real FE Civil exam has 110 questions over 15 topics. This short version keeps the same balance: every topic gets at least one question, and the heaviest topics on the real exam (water resources, structural, geotechnical, transportation and statics) get two. Give yourself about 3 minutes a question, the pace you need on test day, and keep the handbook open, since that is the only reference you get in the testing center.
Mathematics & Computational Tools
Q1A particle moves along a line with position s(t)=t3−6t2+5 (meters, seconds). What is its acceleration at t=3s?
Worked solution
Acceleration is the second derivative of position. First derivative (velocity): v(t)=3t2−12t. Second derivative (acceleration): a(t)=6t−12. At t=3: a(3)=18−12=6 m/s squared. The value -9 is the velocity at t=3 (v(3)=27−36=−9), the classic mistake of stopping at the first derivative. The value 0 is the velocity at the turning point, and 18 is 6t without the constant.
Velocity is the first derivative:
v(t)=3t2−12t
Acceleration is the second derivative:
a(t)=6t−12
Evaluate at t=3:
a(3)=6(3)−12=6m/s2
FE Reference Handbook 10.6, p. 102
Probability & Statistics
Q2A contractor weighs two mutually exclusive bids on a culvert job. Bid A nets a profit of 40,000 dollars with probability 0.6 or a loss of 10,000 dollars with probability 0.4. Bid B nets a profit of 25,000 dollars with certainty. Based on expected monetary value, which bid is preferred and by how much?
Worked solution
Compute the expected value of the risky bid: E(A)=40,000(0.6)+(−10,000)(0.4)=24,000−4,000=20,000 dollars. Bid B is a certain 25,000 dollars. Since 25,000>20,000, Bid B is preferred by 5,000 dollars. "Bid A, by 5,000 dollars" reverses the comparison, picking the risky bid. "Bid B, by 15,000 dollars" uses 15,000 dollars, which comes from treating the loss as a positive payoff so that E(A)=24,000+4,000=28,000 and then taking the wrong difference. "They are equal" ignores the probability weighting entirely.
Expected value of Bid A (keep the loss negative):
E(A)=40,000(0.6)+(−10,000)(0.4)
Evaluate each term:
24,000+(−4,000)=20,000 dollars
Bid B is certain:
E(B)=25,000 dollars
Compare and take the difference:
E(B)−E(A)=25,000−20,000=5,000 dollars (Bid B preferred)
FE Reference Handbook 10.6, p. 67
Ethics & Prof. Practice
Q3Under the typical Model Law experience schedule, a bachelor's degree from an EAC/ABET-accredited program requires four years of qualifying experience for PE licensure, a master's reduces the requirement to three years, and a doctorate (with the FE passed) reduces it to two years. An engineer earns an accredited bachelor's degree, works for one year, then completes a master's degree, and afterward continues working. The one year worked before the master's does not count toward the post-degree requirement. How many more years of qualifying experience after completing the master's does the engineer need?
Worked solution
A master's degree sets the qualifying-experience requirement at three years. The one year the engineer worked before earning the master's does not count toward that three-year post-degree requirement, so the full three years still must be completed after the master's. The 2 years option uses the doctorate reduction by mistake. The 1 year option wrongly credits the pre-master's year against the requirement. The 4 years option uses the bachelor's requirement and ignores the master's reduction entirely. The answer is three years.
The highest qualifying degree is the master's, which sets the experience requirement at three years.
Treq=3years (master’s)
The one year worked before the master's does not count toward the post-degree requirement, so it contributes zero.
Tcredit,pre=0
The remaining required experience equals the full three-year post-master's requirement.
Tremaining=3−0=3years
FE Reference Handbook 10.6, p. 8-9, Model Law §130.10 B.2.a
Engineering Economics
Q4A proposed highway widening has a present worth of user benefits of 8,000,000 dollars, a present worth of disbenefits (added noise and property impacts on adjacent residents) of 1,200,000 dollars, and a present worth of agency costs of 5,500,000 dollars. Using the conventional benefit-cost ratio with disbenefits subtracted from benefits, what is the B/C ratio?
Worked solution
Disbenefits are negative effects on the public, so they are subtracted from the benefits in the numerator: B/C=(B−D)/C=(8,000,000−1,200,000)/5,500,000=6,800,000/5,500,000=1.24. The 1.45 option ignores the disbenefits entirely (8,000,000/5,500,000). The 1.19 option incorrectly adds the disbenefits to the cost denominator (8,000,000/6,700,000). The 1.86 option incorrectly subtracts the disbenefits from the cost denominator (8,000,000/4,300,000) instead of from the benefits.
Subtract disbenefits from benefits in the numerator:
B−D=8,000,000−1,200,000=6,800,000
Divide by the present worth of agency costs:
B/C=5,500,0006,800,000=1.24
Since B/C = 1.24 > 1, the project is economically justified.
FE Reference Handbook 10.6, p. 237, Benefit-Cost Analysis
Statics
Q5A beam has a pin at A (left end) and a roller at B located 8 m to the right of A. The beam extends 2 m past B as an overhang, and a single 10 kN downward load is applied at the free tip of the overhang (10 m from A). What is the vertical reaction at A?
Worked solution
Sum moments about B to eliminate By and find Ay directly, or sum moments about A to find By first. Taking moments about A: By(8)−10(10)=0, so By=12.5 kN. Then ∑Fy=0: Ay+12.5−10=0, giving Ay=−2.5 kN, i.e. 2.5 kN downward. The overhang load actually pulls the pin down (it acts as a tie-down). The 12.5 kN upward choice reports By instead of Ay. The 5.0 kN choice splits the load evenly, valid only for a midspan load between the supports. The 2.5 kN upward choice has the right magnitude but the wrong direction, and the sign matters here because an overhang can reverse the reaction.
Sum moments about A (CCW positive), load is 10 m from A, By is 8 m from A:
By(8)−10(10)=0⇒By=12.5kN
Apply vertical equilibrium:
Ay+By−10=0⇒Ay=10−12.5=−2.5kN
The negative sign means Ay acts downward, so the pin holds the beam down against the overhang load:
Ay=2.5kN (downward)
FE Reference Handbook 10.6, p. 95, Equilibrium Requirements
Statics
Q6A solid rectangle is 100 mm wide and 120 mm tall. A 40 mm wide by 40 mm tall rectangular notch is removed from the top, centered horizontally, with its top edge flush with the top of the rectangle. What is the distance from the bottom of the section to the centroid (yˉ)?
Worked solution
Treat the notch as negative area. The full rectangle has A1=100×120=12,000 mm2 with centroid at y1=60 mm. The removed notch has A2=40×40=1,600 mm2 with its centroid at y2=120−20=100 mm. Using subtraction: yˉ=(12,000(60)−1,600(100))/(12,000−1,600)=560,000/10,400=53.8 mm. Removing material from the top pulls the centroid down below mid-height. The 60 mm option ignores the notch. The 50.0 mm option is the geometric mid-height. The 46.2 mm option over-corrects, as if material were added at the top instead of removed.
FE Reference Handbook 10.6, p. 96, Centroid of Area
Dynamics
Q7A 1,200kg car accelerates from 10m/s to 25m/s on a level road. What is the change in the car’s kinetic energy?
Worked solution
Change in kinetic energy is 21m(v22−v12). Square each speed separately first: 252−102=625−100=525. Then 21(1200)(525)=315,000J. The 135kJ choice squares the velocity difference (25−10)2=225 instead of the difference of squares, giving 21(1200)(225)=135,000J. The 162kJ choice comes from a partial-squaring slip. The 270kJ choice both drops the one-half and uses the squared difference: (1200)(225)=270,000J.
Change in kinetic energy:
ΔT=21m(v22−v12)
Difference of squares (not the square of the difference):
v22−v12=252−102=625−100=525m2/s2
Evaluate:
ΔT=21(1,200)(525)=315,000J=315kJ
FE Reference Handbook 10.6, p. 107
Mechanics of Materials
Q8A simply supported beam of length 6m carries a uniform distributed load of w=8kN/m over only the left half of the span (from the left support to midspan). What is the left support reaction?
Worked solution
The total load is w×(L/2)=8×3=24 kN, and its resultant acts at the centroid of the loaded region, 1.5 m from the left support. Take moments about the right support (B) to find the left reaction RA: the resultant is 6−1.5=4.5 m from B, so RA×6=24×4.5=108, giving RA=18 kN. The 12 kN choice splits the total load evenly (24/2), ignoring that the load is closer to A. The 24 kN choice reports the entire load as the reaction. The 6 kN choice is the right reaction RB=24−18=6 kN, the other support.
Resultant of the partial load:
W=w⋅2L=8×3=24kN at 1.5m from A
Sum moments about B (resultant is 4.5 m from B):
RA×6=24×4.5=108
Solve for the left reaction:
RA=6108=18kN
FE Reference Handbook 10.6, p. 135
Materials
Q9A normal-weight concrete has a specified compressive strength of fc′=4,000 psi. Using the relationship for the modulus of rupture fr=7.5fc′ (psi), the estimated flexural tensile strength is most nearly:
Worked solution
The modulus of rupture estimates concrete tensile (flexural) strength: fr=7.5fc′=7.54,000=7.5×63.2=474 psi. The 30,000 psi choice forgets the square root and computes 7.5×4,000. The 170 psi choice takes the square root of the whole product 7.5×4,000 instead of multiplying by the root of fc′. The 400 psi choice uses the rough 10% rule of thumb (0.10×4,000) rather than the modulus-of-rupture formula the problem specifies.
Modulus of rupture relationship:
fr=7.5fc′
Take the square root of the compressive strength:
4,000=63.2
Multiply:
fr=7.5×63.2=474 psi
FE Reference Handbook 10.6, p. 126
Fluid Mechanics
Q10A water pipe of diameter D=300mm carries flow at v=2m/s into a tee that splits the flow into two pipes of diameter 200mm and 150mm. If both outlet pipes carry the same velocity, what is that velocity?
Worked solution
Continuity at a junction: inflow equals total outflow. Qin=Ainv=4π(0.3)2(2)=0.07069×2=0.1414 m³/s. The combined outlet area is Aout=4π(0.22+0.152)=4π(0.0625)=0.04909 m². With equal velocities, vout=Qin/Aout=0.1414/0.04909=2.88 m/s. The 2.0 m/s choice assumes the velocity is unchanged. The 4.5 m/s choice uses only the 200 mm pipe area. The 8.0 m/s choice uses only the 150 mm pipe area.
Inlet flow rate:
Qin=4π(0.3)2(2)=0.1414m3/s
Combined outlet area:
Aout=4π(0.22+0.152)=0.04909m2
Outlet velocity (equal in both pipes):
vout=AoutQin=0.049090.1414=2.88m/s
FE Reference Handbook 10.6, p. 185
Surveying
Q11A borrow pit yields 5,400 yd3 of bank (in-place) material. The soil has a shrinkage of 15% when compacted in the fill. How many cubic yards of compacted fill does this produce?
Worked solution
Shrinkage means compacted fill occupies less volume than the bank material it came from. Compacted volume = bank volume ×(1−shrinkage)=5,400×(1−0.15)=5,400×0.85=4,590 yd³. The 6,210 yd³ choice adds 15 percent instead of subtracting it. The 810 yd³ choice reports only the lost volume (5,400×0.15). The 6,353 yd³ choice divides by 0.85 (that direction is for finding required bank volume from a known fill).
Apply the shrinkage factor to the bank volume:
Vfill=Vbank(1−S)=5,400(1−0.15)
Compute:
Vfill=5,400×0.85=4,590 yd3
FE Reference Handbook 10.6, p. 315
Water Resources & Env.
Q12A hydraulic jump in a wide rectangular channel has an upstream (supercritical) depth of y1=0.5m and a downstream (subcritical) conjugate depth of y2=2.5m. What is the energy lost across the jump?
Worked solution
When both conjugate depths are known, the energy loss has a closed form: ΔE=(y2−y1)3/(4y1y2). ΔE=(2.5−0.5)3/(4×0.5×2.5)=(2.0)3/5.0=8/5=1.60 m. The 6.40 m option omits the factor of 4 in the denominator: (2.0)3/(0.5×2.5)=6.40. The 2.00 m option just reports the depth difference y2−y1=2.0. The 4.00 m option drops y2 from the denominator: (2.0)3/(4×0.5)=4.00.
Energy loss across a hydraulic jump:
ΔE=4y1y2(y2−y1)3
Substitute:
ΔE=4(0.5)(2.5)(2.5−0.5)3
Compute:
ΔE=5.0(2.0)3=58=1.60m
FE Reference Handbook 10.6, p. 303
Water Resources & Env.
Q13A wastewater sample has an ultimate BOD of L0=320mg/L and a decay rate of k=0.18day−1 (base e). What is the BOD remaining (not yet exerted) after 4 days?
Worked solution
BOD remaining is the organic matter not yet decomposed: Lt=L0e−kt=320e−0.18×4=320e−0.72=320(0.487)=155.8 mg/L. Note the BOD exerted (L0(1−e−kt)=164.2) plus the remaining (155.8) sum to the ultimate 320. The 164.2 mg/L choice gives the BOD exerted rather than remaining. The 57.6 mg/L choice applies kt as a percentage (0.18×4=0.72, then 320×0.18=57.6), a formula confusion. The 320 mg/L choice reports the ultimate BOD, as if no decay had occurred.
BOD remaining (decay form):
Lt=L0e−kt=320e−0.18×4
Evaluate the exponent:
e−0.72=0.487
BOD remaining at 4 days:
Lt=320×0.487=155.8mg/L
FE Reference Handbook 10.6, p. 327
Structural Engineering
Q14A heavily loaded transfer girder supports D=100 kips and a small floor live load L=10 kips (no snow, wind, or seismic). Which LRFD combination controls and what is the controlling factored load?
Worked solution
Combination 1 is 1.4D=1.4(100)=140 kips. Combination 2 is 1.2D+1.6L=1.2(100)+1.6(10)=120+16=136 kips. Because dead load dominates and live load is small, Combination 1 (140) produces the larger factored load and controls. This is the case the 1.4D combination exists for. The 136 kips option is Combination 2, which is smaller here. The 120 kips option keeps only the 1.2D term and drops live load. The 110 kips option is the unfactored service load D+L.
Combination 1:
1.4D=1.4(100)=140 kips
Combination 2:
1.2D+1.6L=1.2(100)+1.6(10)=136 kips
Controlling: Combination 1 at 140 kips (dead load dominates).
FE Reference Handbook 10.6, p. 278
Structural Engineering
Q15A fully braced W-shape has Zx=100 in3 and Fy=50 ksi. What is the ASD allowable flexural strength Mn/Ωb?
Worked solution
With full bracing, Mn=Mp=FyZx=50×100=5,000 kip-in =416.7 kip-ft. For ASD, divide by Ωb=1.67: Mn/Ωb=416.7/1.67=249.5≈250 kip-ft. The 417 kip-ft choice is the nominal Mn without applying Ωb. The 375 kip-ft choice is the LRFD design strength ϕbMn=0.90×416.7, but the problem asks for ASD. The 278 kip-ft choice uses an incorrect Ωb=1.50.
Plastic moment:
Mp=FyZx=50×100=5,000 kip-in=416.7 kip-ft
ASD allowable strength:
ΩbMn=1.67416.7=250 kip-ft
FE Reference Handbook 10.6, p. 287
Geotechnical Eng.
Q16A profile has 4 ft of moist sand (γ=118 pcf) above the water table, then saturated sand (γsat=128 pcf) below it. What is the effective vertical stress at a point 6 ft below the water table?
Worked solution
Total stress: σ=118(4)+128(6)=472+768=1,240 psf. Pore pressure (6 ft below WT): u=62.4(6)=374 psf. Effective: σ′=1,240−374=866≈865 psf. Or use buoyant weight: σ′=118(4)+(128−62.4)(6)=472+393.6=865.6 psf. The 1,240 value is the total stress without subtracting pore pressure. The 394 value is only the buoyant contribution of the saturated zone, missing the moist sand overburden. The 766 value comes from an error in handling the pore pressure or zone thickness; it does not match either the correct method (865 psf) or the listed partial methods.
Total stress:
σ=118(4)+128(6)=472+768=1,240 psf
Pore pressure (6 ft below WT):
u=62.4×6=374.4 psf
Effective stress:
σ′=1,240−374=865 psf
FE Reference Handbook 10.6, p. 269
Geotechnical Eng.
Q17A flow net beneath a sheet pile has Nf=5 flow channels and Nd=10 equipotential drops. With k=1×10−4 m/s and a total head loss of H=8 m, what is the seepage per unit width?
Worked solution
q = kH(Nf/Nd) = (1×10⁻⁴)(8)(5/10) = (1×10⁻⁴)(8)(0.5) = 4.0×10⁻⁴ m³/s per m. The 1.6×10⁻³ option inverts the ratio (uses Nd/Nf = 2). The 8.0×10⁻⁴ option drops the ratio (uses 1.0). The 2.0×10⁻⁴ option halves the head (uses H = 4).
Apply the flow-net formula:
q=kHNdNf=(1×10−4)(8)(0.5)
Compute:
q=4.0×10−4 m3/s per m
FE Reference Handbook 10.6, p. 298
Transportation Eng.
Q18A horizontal curve has R=1,000 ft and intersection angle I=40°. What is the middle ordinate M?
Worked solution
M=R[1−cos(I/2)]=1,000[1−cos(20°)]=1,000(1−0.9397)=1,000×0.0603=60.3 ft. The 234 ft choice used cos(I)=cos(40°)=0.766 instead of cos(I/2): 1,000(1−0.766)=234. The 64.2 ft choice is the external distance E=R[1/cos(I/2)−1]=1,000(1/0.9397−1)=64.2, not the middle ordinate. The 30.2 ft choice halved the correct answer.
Middle ordinate:
M=R[1−cos(2I)]=1,000[1−cos(20°)]
Evaluate:
M=1,000(1−0.9397)=60.3 ft
FE Reference Handbook 10.6, p. 309
Transportation Eng.
Q19An embankment requires 9,000 yd3 of compacted fill. The borrow soil has a shrinkage factor such that compacted volume is 0.90 times the bank (in-place) volume. How many cubic yards of bank material must be excavated from the borrow pit?
Worked solution
Compacted volume =0.90× bank volume, so bank volume = compacted volume /0.90=9,000/0.90=10,000 yd^3. Soil shrinks when compacted, so you must dig MORE bank material than the finished fill volume. The 8,100 yd^3 option multiplied by 0.90 instead of dividing: 9,000×0.90. The 9,000 yd^3 option ignored shrinkage entirely. The 9,900 yd^3 option added 10% instead of dividing by 0.90.
Relationship:
Vcompacted=0.90×Vbank
Solve for bank volume:
Vbank=0.909,000=10,000 yd3
FE Reference Handbook 10.6, p. 315
Construction Eng.
Q20A drainage project reports at month 8: budgeted cost of work scheduled = 1,200,000, budgeted cost of work performed = 1,050,000, actual cost of work performed = 980,000. What is the cost variance, and is the project over or under budget?
Worked solution
CV=BCWP−ACWP=1,050,000−980,000=+70,000. A positive cost variance means the work performed is worth more than what was spent, so the project is under budget. The −150,000 option computed the schedule variance (BCWP−BCWS=1,050,000−1,200,000) instead of the cost variance. The −70,000 option flipped the sign by subtracting in the wrong order. The +220,000 option used BCWS−ACWP, which is not a standard variance.
Cost variance:
CV=BCWP−ACWP=1,050,000−980,000=+70,000
Positive CV means earned value exceeds actual cost: under budget.
FE Reference Handbook 10.6, p. 316
20 questions. Your score shows here as you go.
Practice one topic at a time
Every topic has its own free page of practice problems with worked solutions.